Çankırı Wastewater Project

Priority area

Water (infrastructure related activities) / Environment and Climate Action

Beneficiary

Çankırı Municipality

Duration

Wastewater Treatment Plant 27 months
February 2022 – May 2024

Wastewater Collection System 24 months
December 2021 – December 2023

EU contribution (Euro)

24.969.000

Brief description of the project and main objectives

Construction of wastewater treatment plant and wastewater collection system.
Improving the water quality of Acıçay and Tatlıçay creeks via reducing pollution load caused by untreated wastewater discharge in the existing situation and contribute to improvement of public health.
Overcoming the operational problems in the sewerage system through construction of wastewater network.

Location

Çankırı

Achievements / expected outputs

Wastewater treatment plant and wastewater collection system.
With the construction of the wastewater treatment plant, the needs of the region in terms of wastewater treatment services will be met until 2047..